Tender lead time calculation
We are in 6.3.2
Tender lead time - 2 days
Transit time - 3 days
Late delivery date - May 09, 2014.
Hold as late as possible - True, date emphasis - DELV
Day duration rate service with calendar, Monday to Friday working days.
Same parameter set used for Rate and Route inquiry as well as bulk plan.
In this setup, if I plan an order on May 06, it has 3 days transit (May 7, May8, May 9) and it uses the rate offering with tender lead time = 2 DAYS (where delivery window > tender lead time)
If my tender lead time is 3 days, the same order skips this rate offering (delivery window < = tender lead time). This is in planning.