edited May 21, 2014 1:00AM in Procurement - EBS (MOSC) 3 commentsAnswered

Approver not able to approve requisitions created in Previous period which is now closed.

PR created in Apr-14

Apr-14 GL period is closed.

Approver tries to approve same PR in MAy-14

Getting Error as Not able to derive Gl date.

We are using Encumbrance Accounting (Project Costing). Requisition is related to Project.