Hi,

We're using E1 9.0 release. I'm trying to run R3007G resource unit generation with following PO values & Data Selection.

PO                                             Data Selection

From- 01/01/2014                         Branch- 955B0

Through- 31/12/2015

Workday Calendar- Set for 5 years in Future & 3 in past

Resource unit generation output only gives 1 year data in P3007, Its not going beyong 2014 year.

Is there any setup i'm missing here ?

Regards

Pankaj Sharma