Data Mapping Question for MSP XML Import to P6
I recently imported a large MS Project file (XML format) into P6 and overall am pleased with the results. The structure, dates and linked activities are all there and correct. The only data that didn't come through was custom coded Task information from primarily Outline Code and Flag type fields and also notes. During the import process I selected the 'MSP Mapping' template option but it seems a custom template would be needed in this case. Is this correct and can this type of information transfer via an XML import? If so I'm looking for assistance to point me in