Flow Manufacturing - Automatic delink of Schedule when SO LIne is cancelled

edited Jun 25, 2014 5:00AM in Discrete Manufacturing - EBS (MOSC) 2 commentsAnswered

Can anyone please confirm whether the following functionality works in R12 or NOT. It did work in 11i

1. Flow schedule is created and linked to a Sales Order Line ( SO Line status = Awaiting shipping)

2. The Sales Order Line is then cancelled

Expected Result: The Sales Order Line is cancelled and the Sales Order is automatically delinked from the Flow Schedule (this is what happenned in 11i)

Actual Result: The Sales Order Line is cancelled BUT the Sales Order still shows as Linked against the Flow Schedule in the Scheduling Workbench

Regards,

Brian

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center