P6-Unifier Cost Interface Malfunctioning
Good evening,
I am currently configuring Primavera Unifier to import Cost Data from a project in Cost Sheet. In my P6 Schedule I have activities with Resource Assignments (Labor Resources and Material Resources) and Expenses Assignments. I am able to send Cost information from Labor and Material Resources to the Non-Labor Cost Column in Primavera Unifier but not able to fill in Labor Cost and Fixed Cost Columns in Primavera Unifier. I need to reflect more information regarding Costs from mi P6 Schedule into Primavera Unifier in order for this information to be shown in the Cost Sheet.
My current Status is as follows: