Past Due in ASCP
Hi All,
We are exploring an option to stop PAST due Planning in ASCP.
The issue is collections. In order to make the ASCP plan available on time next day we need to run collections at 8:30 PM EST.
However the shift ends at 11:30 PM EST.
Now whatever operations happen between this are not known to ASCP and ASCP starts flagging them as Past Due.
Normally planners know whats happening on shop floor today as well.
We are looking for an option to start ASCP planning from Tomorrow onwards. We do not want ASCP to plan for yesterday and today.
Is it possible to use any offset so ASCP start planning from tomorrow onwards?