We are on R12 and have scheduled Min Max Planning report to generate requisitions automatically. It was generating seperate requisition for each supplier, however, now it generated only 1 requisition for all the suppliers. I don't remember changing anything except Demand Cutoff Date and Supply Cutoff date parameter from +365 to -30. I doubt that this might have caused it and need some thoughts.