Set ATP rule to consider on-hand stock availability of Raw Materials
HI all,
I hope you can help me. I need to know if is possible to setup the ATP rule for finish goods, to calculate the availability of raw materials.
i.e. I defined two FG, each FG have a common RM (RM1001)
Assembly | BOM Components | BOM Quantity |
F100001 | RM1001 | 5 |
RM1002 | 4 | |
F200001 | RM1001 | 6 |
RM1003 | 3 |
I have a sales order for FG100001 (10 EA) that means i would need 10*5 of RM1001
the second SO is for FG200001 (10 EA) that means i would need 10*6 of RM1001
On-hand for RM1001 is 50
Lead time for RM1001 is 5 days
Lead time for each FG is 8 days