Project Performance Reporting - Issues with generating scores
Hi,
We are trying to setup Performance (Exceptions) Reporting, but despite defining Performance Rules and assigning the rules to a Project, I am not getting any information when I go to the Project Management Reporting tab of the project.
Setup done:
1) Create Performance Rule:
Rule 1
Measure: ITD Burdened Cost + Committed Cost
Thresholds:
0 to 1000 = 'On Track' and do not report as exception
1001 to 100000 = 'At Risk' and report as exception
100001 to 999999 = 'Critical' and report as exception
2) Navigate to Project and to Project Reporting Tab
Go to setup
Update Perfromance Rule Selection, selec Rule1 created in step 1
3) Run PRC: Update Project and Resource Base Summaries & PRC: Update Project Performance Data to get the latest data for the project loaded