Period end accrual impact in Project expenditure entry

edited Jul 21, 2014 5:00AM in Projects - EBS (MOSC) 10 commentsAnswered

Hi Folks,

I want to get confirmation on  PA expenditure integration with PO  module with period end accrual process.

1, We have created a PO with Period end accrual option , approved, receive items against PO   on 01-Jun-2014

2. Closed Period of Jun-14 , then system generated period end accrual entry in costing module

3. Ran  Ran PRC: Update supplier cost program  to update supplier costs in PA module

Question 1:- Will system transfer period end accrual to projects? if not why ?

4. Open  Jul-14 period, system will reverse earlier entry (Step 2 level entry)

Question 2:- Will system resend these reversals to projects?

If period end accruals will not transfer to PA, what is the reason?

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center