New Requirment in the EDD Plan
Hi Gurus,
Need your Advise on the Below Scenarios
In a Same Plane - The Planned Order Generated for Finished Goods Should not Include Purchase Lead Time,
Where as the Planned Order Generated for the RAw Material Should Include Purchse Lead Time
For Example
FG1 - 20000 Forecast DAte ( 01 - Aug-2014)
RM 1 - 100 ( Required ) ( Processing Lead Time 10 days)
RM 2 - 500 ( REquired) ( PRocessing Lead Time 5 Days )
RM 3 - 600 ( REquired) ( Processign Lead Time 3 Days)
Planned Order in ASCP
FG1 - 20000 Qty ( 01-Aug-2014)
RM1 - 100 ( 10-Aug-2014)
Rm2 - 500 ( 05- Aug -14)
RM3 - 600 ( 03- Aug-2014)
( Late Pegging is ok For Raw Materials, so that user can check and Reschedule the Orders)