Cost Group Transfer
Hello All,
We are trying to do a Cost Group Transfer from Material Work Bench (Inventory) for "Item A" .
Scenario :
On hand Quanity for Item A in entire sub-inventory is -1.24995
On hand Quantity in Cost Group 1 (CG1) is -2.999988
On hand Quantity in Cost Group 2 (CG2) is 1.74993
When we tried for Cost Group transfer from CG2 to CG1
Ourr expectation is CG2 transfered to CG1 and the On hand Quantity in CG1 should be -1.24995
But the system is behaving as follows.
On hand Quantity in CG1 becomes -4.24983 and
On hand Quantity in CG2 becomes 2.99988
Please help us on this issue.