R12 - Drop Ship - Schedule ship date adjust on sales order
Hi
Oracle Applications : 12.1.2
Is it possible to reflect a change in the PO ship date back onto the original Sales order?
- We raise a sales order for drop ship with schedule ship date of 25.07.2014
A PO is auto created with schedule ship date of 25.07.2014
- The supplier informs that he cannot ship until 28.07.2014 so the PO is updated manually.
- The updated date is not reflected back on the SO and the SO cannot be updated manually as it's linked to a PO.
Joanne
0