P6 Progress Reporter - Add Activity window - Project Name column

edited Jul 25, 2014 2:25PM in Primavera (MOSC) 2 commentsAnswered ✓

The Progress Reporter Project Name column in the "Add Activity" window (timesheets) is showing the WBS name for the activity, and not the project name.

The PR help file states:

Project Name

The name of the project associated with the activity.


Does anyone know of a configuration setting for this, or is it really a bug?

Thanks,

Todd