edited Aug 18, 2014 5:00AM in Cost Management - EBS (MOSC) 2 commentsAnswered

Requirement is to have Material Overhead absorbed as Percentage of total value for Final Assembly only.

No Material Overheads are defined for all components.

I did the setup specific to WIP Completions. However, When I complete a job, I could not see Material Overheads on Assembly.

I tried to put material overhead for one of the components, and then I retested the WIP Completion. It worked.

So I assume that one of the components should have Overheads defined  with value more than 0, else Assembly will not have Material Overheads. Am I right?

We are using Avg Costing

Thanks in advance for your pointers.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center