URGENT - Material Overhead Absorbtion - Not Working
Requirement is to have Material Overhead absorbed as Percentage of total value for Final Assembly only.
No Material Overheads are defined for all components.
I did the setup specific to WIP Completions. However, When I complete a job, I could not see Material Overheads on Assembly.
I tried to put material overhead for one of the components, and then I retested the WIP Completion. It worked.
So I assume that one of the components should have Overheads defined with value more than 0, else Assembly will not have Material Overheads. Am I right?
We are using Avg Costing