MRP Date Calculation
Hi,
I've a Customer demand with following details; While running MRP first DRQJ in P3411 is offsetting by 6 days instead of 7 days Lead time.
F3460
Item DRQJ Qty Customer
CB020ALG0 01/09/14 1000 75377
CB020ALG0 09/09/14 1000 75377
CB020ALG0 16/09/14 1000 75377
Level Lead Time- 7, Freeze Fence- 7, Generation Date- 01/09
F3411 output
Item DRQJ Qty Lead Time
CB020ALG0 02/09/14 1000 7
CB020ALG0 08/09/14 1000 7
CB020ALG0 16/09/14 1000 7
First bucket is offset by 6 days. Anyone can explain Date calculation for the First period?