PM - Tolerance in Days
Hi,
I have a PM Schedule for an Asset/Activity.
The 'Base Interval in days' = 91 days.
For the Activity the Tolerance in days = 45 days.
No Suppression is defined for the Activity.
Last Service date = 08/04/2014
When I run the Simulation process I get the next work order Suggested: 12/18/2014.I expect it to be 11/3/2014.
For some reason it add the 45 days to the 11/03/2014.
Does anyone have any idea why?
Thanks,
Gilad