Constraint Plan Suggested delivery date issue
Hi,
we have raised a SO for Quantity 30 of an item.
Request date '26-AUG-2014 18:04:25'
Schedule ship date '26-AUG-2014 23:59:00'
after we ran constraint plan suggested delivery date is '10-OCT-2014 23:59:00'.
we are using Enforce Capacity Constraints and our supplier has ' 1 ' Capacity Per Day. we are using 5 day a week calendar.
any inputs regarding how suggested delivery date is decided will be appreciated. Thank You