EDD Plan Configuration
Hi All,
I need some ideas on EDD Plan configuration.
We are trying to achieve -
- ASCP Plan should use substitute components
- Plan should NOT respect manufacturing lead time and the resource constraint. We are Ok with violation of Mfg Lead Time and overloading resources
- Plan MUST respect any Purchasing constraint. If we cannnot get component on time then plan should fulfill demand late but not before evaluating substitute components and/or alternate supplier
The configuration I have done is -
- EDD Plan
- NO Resource Constraint
- No SDS Constraint
- Only Supplier Capacity Constraint - However no supplier capacity setup in ASL on source