P48013, manufacturing program.
I have a question, with the correct use of P48013, manufacturing program.
The following example is real in my company:
There is a work order for the 15th of September, the date on which it is planned on September 10, and the start date is September 09, according to lead time of 6 days.
By doing the work order (WO):
Dates (DRQJ) = 15-09-14
Date planned (DPL) = 15-09-14
Date start (STRT) = 10-09-14
How I can stop the scheduled date for the day 09-09-14, since the system when saving the order equals dates.