Working with dates MRP ???
When I work with dates of MRP,
For the generation of purchase orders, application date (DRQJ) is the program that will use the P4310 as promised delivery date.
I need the date of delivery of the supplier either:
Start date P3411 (STRT + LEAD TIME Item of the P41026.)
is possible. ???
For example:
Item P3111 (DRQJ) = 15-SEP-2014
Item P41026 purchase lead time = 10 days
today runs the MRP:
the Message (O)
now + the lead time = (12-SEP-2014 DRQJ P3411)
What I need is that the items purchased are not delivered the same day as the start date of the WO.
Regards.
Mario