Can't delete start date so logic does not flow
I have a start date on all of the activities in my schedule. It correlates to my data date, but I did not deliberately set it. Now, my logic does not flow based upon predecessors. Each item starts on the data date. How do I cure this? The system will not let me delete the start date without inputting another. I believe that my initial set up is probably wrong. But I have not been able to pin down what I should change.