WIP Component Pick Release by requirement date

edited Mar 3, 2016 4:05AM in Discrete Manufacturing - EBS (MOSC) 1 commentAnswered

We are on 12.1.3 and use WIP.

There are two work orders 1234 and 1235

1234 needs component C1 for qty 1 on 10-sep-14

1235 needs component C1 for qty 1 on 10-jan-14

Onhand for C1 is 1

If we run component pick release with from job# as 1234 and to job# as 1235. even though 1235 needs component C1 before 1234 , system allocates the component C1 to 1234 and not to 1235 because 1234 comes before (in terms of numbering ) 1235

Is there any way we can have the system do component allocation for pick release based on dates or some other priority rules?

thanks

rahul

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center