Field Service - EBS (MOSC)

MOSC Banner

Why is the Planned effort field on the task always considering 24 Hrs as 1 Day rather it should cons

edited Sep 30, 2014 5:01AM in Field Service - EBS (MOSC) 4 commentsAnswered

Hi All,

Why is the Planned effort field on the task always considering 24 Hrs. as 1 Day rather it should consider 1 Day based on the assigned technician shift timing.? Is there anyway to achieve the same?

If I enter Schedule Start Date - 16-Sep-2014 8:00:00 & Schedule End Date - 16-Sep-2014 16:00:00, where the assigned technician shift timing is 8 HRS, the planned Effort is changing to 0.33 Days which is incorrect.

Thanks & Regards,

Pavithara

Message was edited by: Pavithara

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center