Demand Class ATP Not Working
Hi All,
I am trying to setup demand class ATP.
The idea is that we already know the capacity we want to dedicate to some key customer.
I have setup demand classes for them.
Based on this we have published forecast for each demand class.
ONLY FOR TESTING purpose I have following setup -
Demand classes -
GOLD
SILVER
OTHERS
Forecasts -
GOLD - Only in NOV 2014
SILVER - Only in DEC 2014
OTHERS - Only in JAN 2015.
This tells that any demand from GOLD will be fulfilled in NOV 2014.
Demand from SILVER will be fulfilled in DEC 2014
Demand from OTHERS will be fulfilled in JAN 2015