edited Oct 6, 2014 10:01AM in Projects - EBS (MOSC) 5 commentsAnswered

We are trying to adjust the burden multiplier in order to get more revenue on a project. However Oracle does not recognize these changes.

We have executed the following steps to recalculate revenue:

1. We had changed the burden multiplier under the burden schedule overrides at the project level and then compiled the change, after which we got a popup saying 1 record applied and saved.

2. Then in the expenditure inquiry, we selected all the expenditure items and from the tools menu clicked on "Recalculate Revenue" and we got a note "23 item (s) adjusted successfully.

3. Then we ran the PRC: Generate Draft Revenue for a Single Project program.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center