Do we need to setup another eAM enabled Org with costing type of standard for items that use Standar
Hi,
Currently we have an eAM enabled org with average costing, but some items need to be on standard costing. We tried to transfer items from IO (standard costing) to eAM Org (Average) but upon material issuance to WO it follows the costing under average.
I noticed also that after the Inter-Org transfer, items transferred to eAM Org have zero cost, why is that? Any idea?
Thanks,
Chris