ASCP resource requirement not used actual assigned unit number in routings and discrete jobs.
Hi,
I'm trying ECC plan of ASCP with Discrete manufacturing.
I would like same schedule result between ASCP and WIP.
And, I set assigned unit number in operation resources of Routing > 1.
And, i can see correct information in collection workbench(view collected data>item>routing operations>resource) and planner workbench(planner workbench>item>routing operation>resources).
But, I can not see correct assigned unit number in resource requirements of Plan result. (please refer to my attachment)
And schedule time also not same as discrete jobs.
And i can see correct assigned unit number in "LOT" basis resource. but almost schedule time is based on "Item" basis resource.