Manufacturing - JDE1 (MOSC)

MOSC Banner

r31802A

edited Oct 14, 2014 10:00AM in Manufacturing - JDE1 (MOSC) 2 commentsAnswered

We are running work orders for an item where the primary UOM is KG. The BOM requires .86 KG of a component costing $11000 per KG. The BOM contains other items. We complete the work order and we run R31802A. We notice that if we run this program for this order only, the cost of this component shows up correctly at $9460. However, when we run R31802A for all the work orders completed during the day (around 50 WO's), the same cost of this component is calculated as $11,000. Somehow it seems that the quantity in this scenario is getting rounded to 1.

Has anyone come across such an issue?