Hi team is any one currently using the DRP application for deploying FG inventory from the plants to
We are testing the 12.3 fair share functionality to deploy finish good inventory out to our distribution facilities from our plants. It seems that we have a need to re run the DRP plans at least 3 times per day in order to pick up and net unexpected demand occurring on a regular basis.
Currently to run our DRP plan for all Orgs takes up to 8 hours today. I was wondering how other businesses with similar issues were addressing this issue.
Thanks in advance for your help