Hi Team,

For a particular item MAKE Item the scenario is For a same item which is planned in MPS and MRP but the action status show in workbench is different .

like in MPS for the item X it shows rechedule and for same Item in MRP plan it shows Cancel why? how can we avoid ?

secondly

for some items there are work orders which are present but there is no planned order generated hence the BOM is not exploded. Morover the Action status is in CANCEL/ Reschedule Out.

Please clarrify for second scenario for above action items CANCEL/RESCHEDULE there is no pegging would be calculated ?

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center