Create Planned orders (2 weeks) Early specific to customers
Hi,
I want to create planned orders two weeks earlier than expected but without changing Sales order SSD.
Eg . customer A placing sales order for item B with requested Date : 31-DEC-2015 from DC1(warehouse).
When sales order is booked CRSD and SSD = 31-DEC-2015
Item B is make item in DC2 (manufacturing site) with manufacturing lead time : 5 days.
Transit lead time between DC2 and DC1 is 5 days.
Post processing lead time is 1 days.
So currently Planned order is generated in DC1, requesting materials 11 days early only ie(19-DEC-2015).
I want to create planned orders two weeks earlier. how should i achieve this. i want to create planned orders 05-DEC-2015 itself.