ASCP does not create Planned Orders if Sourcing Rule is switched to Single Source
We are 12.1.3 Version . We have defined sourcing Rule with Supply from two Sources - 50% from Supplier and 50% from Transfer from Other . Then switched the Source to Single - 100% purchase from Supplier. We have Firm requisitions for transfer and it existed for six months from now and it won't cater the entire Demand. Expectation is ASCP should will respect the Firm planned orders and suggest for the Planned orders from Supplier for the balance demand and Once the Firm Requistions are consumed, then all supplies to be planned from Supplier.
Plan Launch Date : 30 Oct 2014
But we had the following result
1. Firm Requisitions are respected and but the new planned Orders has been created with Supplier only from March 2015 . Eventhough the Firm Requisitions does not fulfill the demand fully from October 14 to March 15, ASCP does not plan any Plannned Orders to Supplier to the remaning unfulfilled Qty.