We plan to implement Funds distribution functionality for
our client. I am trying to test the below scenario but not sure if this can be
replicated as part of PC Funds Distribution functionality. Here is the scenario
- Create a Project (Proj1) with 3 different Activities in PC BU.
- Attach the above 3 Activity IDs to 3 different Contract with Rate based contract line.
- Create a Project Budget in PC for Project (Proj1 and Activity1 combination) and Finalize it
Now what I want to test is if we can split/distribute the finalized budget (Proj1 and Activity1 combination) among all the 3 project activity above through PC Funds Distribution functionality? How to test this? What steps I need to follow to achieve this in PC Funds Distribution. Also if you have a replication doc with similar scenario (9.1 or 9.2) please share with me.