We have below requirement that
Facts-PPM Schedule Dates are fixed and cant be changed i.e after 28 Days so I have used base date functionality
So PPM WO-1 is created on 30th Nov and next WO-2 suggested by system is on 28th Dec.
This is fine but we need that WO-2 of 28th Dec should be coming to simulation but it should not be allowed by system to Create the same untill 30th Nov WO is not completed.
Kindly guide if we can cater this situation.
PFA for more clarification.
Note:-Next WO Only functionality didnt resolvee the issue.