Forecasting PM work orders

edited Dec 1, 2014 11:55AM in Enterprise Asset Management - EBS (MOSC) 9 commentsAnswered ✓

I'm having trouble understanding what my forecasted work order dates are based on.  Here is an example:

I have a PM schedule created for an asset.  This is the relevant PM schedule information:

  • Based on meter rules
  • Use actual end date to suggest next service start date
  • In the PM schedule, there is an activity that is set to occur every 2000 meter units (engine hours).
  • The PM screen shows that the current usage rate of this meter is 23.504 (engine hours per day).
  • The last service date for the activity in question is 16-SEP-2014, with a meter reading of 17340.

The most recent meter reading for this asset is 18450 on 01-NOV-2014

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center