ASCP Production sequence is not planned according to change over time

edited May 11, 2015 5:00AM in Value Chain Planning - EBS (MOSC) 10 commentsAnswered

 

We have setup resources to follow production sequence according to change over time. After the plan run we do not see the sequences in accordance with change over time.

 

We have four product families with change over time as given:

 

  • Product family 1  
  • From product family 1  to  product family 2  change over time is  2.5 hours
  • From product family 1  to  product family 3  change over time is  6.5 hours (i.e  from product family 2 to  product family 3 is  4 hours)
  • From product family 1  to  product family 4  change over time is  10.5 hours (i.e from product family 3 to  product family 4 is   4 hours)

  

What we get in ASCP output is bit strange.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center