Confidence% in Forecast Entries
All
Have a question related to Confidence% in manual Forecast Entries
We are on 11510(OLTP) and 1213(ASCP).
In manual Forecast entries, there is a column called Confidence%, as per the MS/MRP userguide, it says
"Enter an optional confidence percentage that the forecasted item will become actual demand. Oracle Master Scheduling/MRP and Supply Chain Planning multiplies this percentage by the forecast quantity when you load it into a master schedule"
My question is will Confidence% taken into consideration in ASCP as well, I didn't get any document. Any pointers / information is highly appreciated
Thanks
J.M