why is the schedule showing an original duration of more days than are actually worked
Received this schedule from a contractor and i noticed that some of the atcvites are indicating an original duration of more than the number of working days the scheduled dates indicated,
for example Activity #1010 indcates and orignal duration of 23 days but the dates only indicated from the 4SEP14 to 01OCT14 or 21 working days
Activity #1A110 indicaes and original duration of 15 but the dates only indicate from 07OCT14 TO 23OCT14 OR 13 WORKING DAYS
These activites are only working monday thru friday so there is no weekend work