Supersedes Patches on top of Oracle Projects Release Update Pack 6 for 12.1 (R12.PJ_PF.B.delta.6)
Hi,
I am have fresh installation of oracle projects at my instance. The current status is:
R12.PJ_PF.B.delta.3.
I want to have R12.PJ_PF.B.delta.6 with recent Patch 17855246: CUMULATIVE RELEASE 5 ON 12.1.3.DELTA.6 ON RELEASE DATE 14-NOV-14.
For this, i have figured out following steps:
Apply Patch 17887429 first
Then Apply Patch 17839156 - R12.PJ_PF.B.delta.6
As suggested in "What is the Correct Order for Applying Patches 17839156 - R12.PJ_PF.B.delta.6 and patch 17887429? (Doc ID 1613813.1)".
This will lead me to delta 6.