OPM Batch Original Planned Start Date in ASCP
We are running an unconstrained plan (R12) and are struggling with determining when an OPM batch should start. Everything shows it's supposed to start either on or after the anchor date. If a batch should have been started 3 weeks ago, it still shows that it should start today. With planned orders, we are able to see compression days to see how far behind we are but we haven't been able to find something similar for batches. We need a method of determining and measuring whether we are starting our batches on time.
Any insight that you can provide would be greatly appreciated.