Primavera Contractor - Durations & Float in Decimal Fractions

edited Jan 16, 2015 11:51AM in Primavera (MOSC) 6 commentsAnswered

I'm a new user of P6 Contractor.

I'm having problems with Duration and Float occurring as fractions. I need whole numbers. I've looked at my calendars, trying to see if this issue is based in a calendar configuration, but I don't recognize a problem. I don't know where to go or look next.

Can anyone help?

Thanks

Tagged:

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.