Planned order start date after firm and release
We have a Planned order for which start date and due date are calculated as below:
start date = Due Date - (in transit lead time) - (post.proc lead time)
we don't have other lead times set up.
Now After the plan run, If we change the due date by firm and releasing it from the workbench, where do we see the newly calculated start date?
Looks like the system is not calculating the new start date(based on the lead times) on the fly , Is it something that we need to calculate?
Any ideas? We are running Constrained plan(ECC with out detail scheduling)