Is there a way to capture negative quantities in supply/demand or MRP messages?  We are using process manufacturing with co/by products however, we are generating a material that will be returned to inventory as a raw material in the bill of materials.  Supply/Demand and MRP messages do not capture these quantities.  Is there a way to include these in the planning process?  We want to procure only the portion of the raw materials requirements not covered by this return to inventory.