Items are not shown/picked up for supply/demand after MRP plan run
Hi All,
Have defined:
- Items FG1 and RM1 with MRP planned attributes
 - Defined BoM and WIP and able to create manual Job
 - Defined Sourcing rule, Assignment set and assign this Assignment set in MRP% ATP Assignment set profile option
 - Defined Forecasts and MDS. Forecasts are appearing in MDS
 - Defined MRP plan and options in Supply Chain Planner > MRP > Names
 - Launch MRP plan.
 - Checked in MRP workbench for supply/demand for the above items, but no results?
 
Please suggest is there any setup am i missing?
Thanks,
Jey