Hi,
We have facing issue with OSP Job as ,
Step 1. Create Non Std WIP Job for rework .
Step 2.Did manually move and completion txn
Step 3.PO requisition trig
Step 4. Fiance team had closing the WIP job by Close Discrete Jobs program
Step 5.OSP resource had received against a Closed Job hence records are error out with message ‘No charges allowed for this job/schedule.’
Is there any way to restrict closer of WIP Job when the OSP resource not charged ? OR any other suggestion to fix this issue ?