Update ASCP Planned order with reference number for Internal Requisition
Requirement is to update the Third party sales order reference number manually in the ASCP Planned orders (any of the available fields) and then release the planned order to create the internal requisition. The updated reference value should be available /viewed in internal requisition after the import.
I have updated the reference number in the Comment field for a Particular Planned order. Then released the order from workbench and requisition got imported successfully, but the comment field data/ co-corresponding field are not in the requisitions
Do we have any workaround?
Regards,
Ramesh