Hi we have a case that on the AR Transaction, one of the line ($300) is to be booked as deferred revenue because a Customer Acceptance contingency is applied. This transaction line also has an Accounting Rule with fixed period for 3 months and start date is 01-Jan-2015. Now if we remove the contingency on 01-Feb-2015, how can we make the accounting rule start also from 01-Feb-2015, and the expected revenue schedule should be : $100 Feb-15, $100 Mar-15, $100 Apr-15.

Any advice?