Sales order quantities to be consolidated in one planned order using MRP

edited Mar 23, 2015 1:35AM in Value Chain Planning - EBS (MOSC) 1 commentAnswered ✓

Using MRP(not ASCP) for planning.

Created 3 sales orders for an Item with Scheduled ship date SO1-Day 12,So2-Day 13,SO3-Day 14 and all with qty 10.

Now i want the mrp to suggest in the same Planned order with qty 30 on Day 14. Basically would like to consolidate the SOs and create a single planned order.

Please suggest the steps to achieve this.